What does this information tell you about this project?
This earned value analysis tells us that the project is behind its original estimate (value) by $20. The PV, or Planned Value, was estimated to be $240; however, the actual amount spent on the project so far (EV or Earned Value) is only $230.
Furthermore, the AC or Actual Cost of this project is higher at $250 which means that more time and money have been spent than originally planned. This indicates that we are 10% behind schedule in terms of completion as well as having an overspend of 20%.
For this reason it is important to identify any potential issues that could have caused these delays and/or cost overruns such as resource shortages or mismanagement of funds/time. Additionally we need to understand how much additional effort will be required in order to get this project back on track and if any changes should be made along with a contingency plan for further unforeseen obstacles.